Local Funding Sources
Sacramento Transportation Authority -- Measure A Sacramento County sales funded projects as of June 2024:
- $44.0 M for purchase of land and historic station (2006)
- $4.72 M for Phase 1 - Track Relocation and new Passenger Platforms & Tunnel (2008-2012)
- $28.15 M for Phase 2 - Historic Station Renovation (2012 – 2017)
- $0.95 M committed to Phase 3 – SVS Area Plan and Site Buildout (2016 to present)
TIRCP Projects:
- Northbound I-5 Ramp Reconfiguration & 3rd Street Extension Study
- SVS-Railyards North Entrance
- SVS PUDO (Pick-up/Drop-off)
- SVS Storm Drain Line Regional Bus Mobility Center Engineering Design & Environmental (NEPA)
- H Street Cycle Track (10th Street to SVS)
- SVS Regional Commuter Bus Stops (Capital Improvements)
- X Street Regional Bus EV Charging Facility (Capital Improvements)
- X Street Regional Bus Facility EV Charging Infrastructure
- Regional (SACOG) Bus Stops 5th Street & North B Tie-in Regional Bus Mobility Center - Construction
For more information, click on SVS Project Funding.